[HN Gopher] How to replace estimations and guesses with a Monte ...
___________________________________________________________________
How to replace estimations and guesses with a Monte Carlo
simulation
Author : lucasfcosta
Score : 364 points
Date : 2021-10-06 04:52 UTC (18 hours ago)
(HTM) web link (lucasfcosta.com)
(TXT) w3m dump (lucasfcosta.com)
| henryaj wrote:
| Worth checking out Guesstimate[0] for a neat tool to help make
| these kinds of estimations.
|
| [0] - https://www.getguesstimate.com/
| adamgordonbell wrote:
| Great tool. I've used Crystal Ball in the past, and this is so
| much easier to use.
| asdf_snar wrote:
| I really dislike posts in this vein, because they use statements
| like
|
| "This post will teach you how to replace estimations and guesses
| with a Monte Carlo simulation."
|
| as though the output of a Monte Carlo simulation were not an
| estimate, but some higher truth. The process of simulating many
| different outcomes with a touch of randomness gives the layperson
| the impression that we are really _doing_ something, when in fact
| we could have obtained the exact result (no confidence intervals
| needed) of Monte Carlo by quadrature (although admittedly that
| could be tedious).
|
| In the end, the method outlined in the link is an estimate, like
| any other, and is not necessarily better or worse than any other
| estimate. It erects a straw person and then misuses mathematical
| terminology throughout.
| xyzelement wrote:
| > It erects a straw person
|
| Just wanted to appreciatively note your use of inclusive, non-
| gendered language here.
| lucasfcosta wrote:
| Author here. Thanks a lot for your feedback.
|
| Indeed, "estimations" might not be the best word as you're
| still, in some way, estimating with the Monte Carlo approach. I
| thought of this differentiation because I consider the MC
| approach to yield a forecast, while an "estimation" is the
| typical term used in agile settings for "guessing how long/much
| work it will take.". I'll think of ways of making this
| distinction clearer.
|
| As for the misused mathematical terminology I guess you're
| referring to "confidence intervals"? If so, I understand it
| also has a clear definition within statistics, but I used it in
| the broader sense. I'd be grateful if you could point out which
| terms you'd recommend replacing and what you think I could
| replace it for.
|
| Thanks a lot.
| asdf_snar wrote:
| > Indeed, "estimations" might not be the best word as you're
| still, in some way, estimating with the Monte Carlo approach.
|
| Not in some way -- literally. The samples are averaged, and
| as the number of samples goes to infinity, the average
| converges to some true value. In the case of one of the
| histograms you plot, you are averaging an indicator function
| .
|
| > I thought of this differentiation because I consider the MC
| approach to yield a forecast, while an "estimation" is the
| typical term used in agile settings for "guessing how
| long/much work it will take.". I'll think of ways of making
| this distinction clearer.
|
| It seems to me the distinction you care for is to provide not
| a single value ("estimate"), but a distribution of values.
| That's not specific to Monte Carlo.
|
| > As for the misused mathematical terminology I guess you're
| referring to "confidence intervals"
|
| That's certainly one of them. I even misunderstood what you
| were doing and said you don't need confidence intervals, but
| in the way you're using them those again can be obtained by
| quadrature.
|
| My main gripe remains the language, and the presentation of
| the method. You could most likely obtain your results by
| hand, i.e. with pen and paper, and you would still get a
| distribution at the end of the day. The advantage of running
| Monte Carlo is that it simplifies this process. You could
| illustrate this by getting the distribution of the sum of two
| independent uniform random variables in two different ways:
| by doing a convolution, and by MC. Wow, MC was so much
| easier, anyone can do it, and it can handle arbitrarily
| complicated distributions (in principle).
| lucasfcosta wrote:
| Understood. Thanks for taking the time to provide more
| detail.
|
| I'll take some time to digest and think through changes,
| and either edit, or write a clarifying appendix.
| [deleted]
| Ma8ee wrote:
| Monte Carlo simulations are often just a relatively easy way of
| doing numerical integrations. But it sounds fancy.
| shapefrog wrote:
| I use Monte Carlo simulations because I am not that great at
| doing complex statistics.
|
| It sounds fancier to say modeled using a Monte Carlo
| simulation, but in reality it is much easier than working
| with joint and conditional probabilities.
| cycomanic wrote:
| I sort of agree with you although for different reasons. The
| problem with the MC approach IMO is not really that it is also
| an estimate, estimates are fine. However doing a Monte Carlo
| simulation is only reasonable if we have a good model. So now
| we have moved from we can't estimate (intuitively I guess) to
| how to find a good model, that is not trivial and the time
| spend on finding and verifying the model might take more time
| than what you are actually trying to do (just an (gu-)estimate
| on my part)
| Jensson wrote:
| A Monte Carlo simulation is infinitely better than all the
| conventional "to estimate, take your first estimate and
| multiply it with 10x". And even better, your manager can do
| that without your help and this learn better how much you
| tend to over/under estimate projects without trying to force
| you to change your estimates to fit what he think it should
| be.
|
| It also ensures that the final estimate becomes on average
| correct, which is much better than most projects which tends
| to under estimate the effort it will take. Although, under
| estimating projects is often a feature managers wants since
| it makes it easier to sell it to customers, ie "My engineers
| estimated we can remake Twitter in a weekend, I think we
| should focus on that!".
|
| Anyway, the point is that if your manager complains about
| your estimations being on average off then he is just
| incompetent and should have applied a Monte Carlo simulation
| on it instead of asking you to perform an easily automatable
| task.
| edu-ap wrote:
| A model is not required if you use data from your team's past
| performance with a tool like this:
| https://marketplace.atlassian.com/apps/1216661/actionableagi...
| zmk_ wrote:
| Which is called bootstrapping.
| twelvechairs wrote:
| For those who like to do things a little more visually I
| recommend the open-sourced Argo[0] for microsoft excel.
|
| There's a lot you can do with a monte carlo model. Tornado plots
| are something I highly recommend for understanding risk profiles
| around any complex task
|
| [0] https://github.com/boozallen/argo/releases
| adamgordonbell wrote:
| This looks great. I wish there were something like this for
| google sheets or that worked outside windows. Guesstimate is
| close to this.
| gpmcadam wrote:
| Shameless plug but we wrote a free tool that you can pipe in Jira
| data and run monte-carlo simulations to help generate forecasts.
|
| If you don't want to go through the process of logging in via
| Jira there is a demo where you can manually input the data
| needed.
|
| See: https://agilytics.leanloop.co.uk
| jcmontx wrote:
| I will definitely be using this! Can I use single project
| analytics instead of the whole jira? (Different people work on
| different projects)
| dantame wrote:
| Yep it will allow you to select a project from your JIRA
| instance and only count throughput from that project in the
| calculations.
| alfonsodev wrote:
| Not to hijack the conversation, but I though some people
| interested in replacing estimations could find this useful.
|
| In order to replace estimation, we are trying Basecamp's Shapeup
| language and techniques [1]
|
| In a nutshell the thinking is reversed, instead of asking:
|
| - "how long would it take to implement X?"
|
| you ask:
|
| - "how much appetite (in weeks and people involved) do I have for
| this feature ?"
|
| Then you work with a fix "dead line" and variable scope.
|
| Instead of user stories, they call it Bets, and they give
| themselves 2 weeks to shape bets and 6 to implement them (these
| two cycles can happen in parallel), during those weeks is about
| leaving the design at the Mockup/sketch level, and identify with
| help of business and technical people all the possible risks, so
| the Bet safe becomes a safer Bet.
|
| We are still in the first cycle, and still a lot of questions and
| doing our own little customisations, but everyone response seems
| to be positive with the way of working, curious if anyone else
| has tried succeed and fail.
|
| - [1] https://basecamp.com/shapeup
| ghiculescu wrote:
| Shape up is a powerful framework, it takes a while to get right
| but it's very worth doing. We are about a year in, still
| improving at it. Our main focus now is doing things more by the
| book and getting rid of the customizations we added in the
| early days - so try and not make too many! :)
|
| Email is in profile if you want to chat more on trade notes on
| it.
| adamwathan wrote:
| We work this way as well and it is wonderful.
|
| We've been doing Shape Up since July 2020 and have yet to fail
| to ship what we shape for each 6 week cycle, and while there's
| sometimes a bit of a crunch in the last few days before a
| release, everyone is generally working at a pretty relaxed
| pace.
|
| My favorite side-effect of working this way as a leader is that
| by batching 6 weeks worth of planning effort, the team (and
| myself) can just be generally left alone to get into it without
| having to decide on the next priority every single week.
| Combined with async check-ins (that the team provide themselves
| every couple of days via Basecamp) instead of daily/weekly
| stand-ups, everyone generally has an empty calendar at all
| times.
| [deleted]
| tchalla wrote:
| Flipping the question within a restricted variable is my
| favorite hack.
|
| Overlords - "How much money do you need for this project?"
|
| Me - "How much money can we spend?" / "How much time should we
| spend?"
|
| Friend- "Look at how much money that CEO earns!"
|
| Me - "What will you give up in your lifestyle to do what the
| CEO does?"
|
| The only challenge though in these situations is that most
| people aren't open enough to do "Think in bets". They either
| avoid the question or don't even attempt to come an answer
| (despite them not spending a single dime!).
| strife25 wrote:
| I used this method for a while on one of my teams. It was useful
| and helped provide more accurate estimates.
|
| Some tips I have for people interested:
|
| * Get about two months of velocity data in place first. * Run the
| simulation on a regular basis. Update your estimates every
| week/sprint. * It helps to have individual work units be "sized"
| as consistent as you can. (E.g. each ticket is 2-3 days, a
| consistent pointing system, etc.) It's ok if anomalies happen
| from time to time. * Dates will get more accurate the further you
| get into a project.
|
| Some things I've learned from doing this exercise:
|
| * When work units are sized to be 2-3 days of effort, engineers
| complete about 4 units/wk on average. * Don't shoot for the
| perfect estimate at the start of a project. Plan as much scope as
| you know and enough to get started. * As new scope is found,
| update your project plan and estimates.
| markmaglana wrote:
| If you already have ~2 months worth of data, why not just use
| that to plot a distribution curve? Seems to me that the monte
| carlo simulation that the article describes is really just used
| to "guess" the likely distribution curve. Seems unnecessary if
| you already have ~2 months worth of data.
| kongin wrote:
| This is a very naive approach for a number of reasons:
|
| 1). You're only sampling a tiny fraction of the space of
| possibilities. The example using two dice having 36 outcomes
| makes it seem like you're in a very well behaved world. But the
| total number of possible samples is n_possible_values ^ n_dice,
| so with three dice you have 216 possible outcomes, with 4 dice
| 1296, with 10 60466176. The growth is exponential in the number
| of variables, with predictable results.
|
| 2). The distribution of delivery times is not normal, experience
| shows it's much closer to a power law with a small number of
| tasks exploding beyond any reasonable expectations.
|
| 3). No critical path. A task can't be completed before it's
| critical path is completed. Since you allow subtasks to vary your
| critical path needs to be calculated for each run. With 1). and
| 2). it basically means that you have no idea if you've gotten a
| good representation of the sample space of critical paths.
|
| If you run a simulation that samples a tiny fraction of your
| probability space you have no idea what monsters lurk in the
| background when the problem space is one prone to explosions.
|
| In short: beware of tap dancing in minefields when blindfolded.
| brightball wrote:
| I'm a big fan of the Donald Reinertsen approach: measure queue
| length.
|
| Simply track the time to complete each task in the team queue on
| average, then multiply that by the number of tasks remaining in
| the queue.
|
| Each team will habitually slice things into sizes they feel are
| appropriate. Rather than investing time to try and fail at
| accurately estimating each one, simply update your average every
| time a task is complete.
|
| The bonus with this approach is that the sheer number of tasks in
| the queue will give you a leading indicator, rather than trailing
| indicators like velocity or cycle time.
| sillysaurusx wrote:
| What do you do when your future tasks are unknown or ambiguous?
|
| For example, at my day job my task is to implement banking. The
| day to day tasks change... day to day. There aren't a "number
| of tasks remaining in the queue," since whatever I'm doing is
| what I'm doing.
|
| One could say this is poor planning. But due to the nature of
| Big Banks, each task is usually blocking the next one -- in
| other words, it's not possible to discover or plan what you
| need to do next, until you've finished currently.
|
| An example of this is when we realized we didn't need to run
| our banking API using $BigBank's test environment. Their test
| environment was ... uh ... well, let's just say, when we
| realized that we could simply switch on "production mode" and
| bypass their test environment altogether, we collectively
| facepalmed while rejoicing.
|
| It wouldn't be possible to add "switch to the production
| environment" into the queue several days ago, because we didn't
| discover that we _could_ do that until yesterday during our
| biweekly sync call.
|
| I'm sympathetic to your writeup, and I like your recommended
| approach. But I just wanted to point out a realistic case of it
| failing. But in fairness, I think every estimation approach
| would fail us, so don't feel singled out. :)
|
| Perhaps your approach will work in most cases though, and I'm
| merely stuck in a twilight zone special case.
| codemac wrote:
| What happens when you complete your work before you know what
| you need to do next?
|
| If this never happens, then you have some invisible queue, as
| you do have things to do next.
|
| As far as your example, that's a great example of a task that
| seemed like it would take long, and ended up being very very
| short. Can you describe why this would be bad to add into
| your task system? - Add Task: Run banking
| API in $BigBank test environment - Start work time
| clock. - Find out we don't need to do it, and switch
| to prod mode - switch to prod mode - Close
| task, and time clock
|
| This is now data for your estimates of future tasks, as this
| will probably happen randomly from time to time in the
| future.
| sillysaurusx wrote:
| Switching to prod mode takes 5 to 7 business days, because
| we have to order certs from DigiCert and then upload them
| to $BigBank, whose team requires 5 to 7 business days to
| activate said certs.
|
| We expected to turn on prod once testing was finished. But
| we ended up discovering that prod was the only correct test
| environment, because their test environment is rand() and
| fork()ed to the point that it doesn't even slightly
| resemble the prod environment. Hence, "prod am become test,
| destroyer of estimates."
|
| So for 5 to 7 business days, we'll be building out our APIs
| by "assuming a spherical cow," i.e. assuming that all the
| test environment brokenness is actually working correctly
| (mocking their broken responses with non-broken responses.)
| Then in 5 to 7 business days, hopefully we'll discover that
| our spherical-cow representation is actually closer to the
| physical cow of the real production environment. Or it'll
| be a spherical cow and I'll be reshaping it into a normal
| cow.
|
| By the way, if you've never had the pleasure of working
| with a $BigBank like Scottrade, Thomson Reuters, or
| $BigBank, let's just say it's ... revealing.
| [deleted]
| codemac wrote:
| Maybe I'm missing your point. It seems you're attempting
| to answer the wrong question: is this task accurate,
| given all the changes that have happened? This is
| irrelevant for large scale estimation.
|
| The question for scheduling prediction is: what
| distribution of time will it take to mark any task in
| this queue as FIXED/INVALID/WONTFIX/OBSOLETE/etc? The
| queue can have any amount of vagueness you want in it.
|
| Regardless of the embedded work, regardless of whether or
| not it changes, becomes invalid, doesn't exist, etc -
| these are all probability weights for any given
| task/project.
| charles_f wrote:
| > The day to day tasks change... day to day. There aren't a
| "number of tasks remaining in the queue," since whatever I'm
| doing is what I'm doing.
|
| What you are describing is not ambiguity, it's total
| variability. If your future is 100% random, it is, by
| definition, impossible to predict. Such a state would also
| mean a total absence of direction/vision. Predicting dates is
| not only impossible but not a question you can ask, since you
| don't know what's next.
|
| What I'm going to challenge is that you're effectively in
| such a case, because I don't think it's true.
|
| > One could say this is poor planning. [...] in other words,
| it's not possible to discover or plan what you need to do
| next, until you've finished currently. [...] because we
| didn't discover that we could do that until yesterday during
| our biweekly sync call.
|
| The example you're giving *is* poor planning. You're going
| into execution without validating base assumptions. That you
| discover the specifics of a dependency that late into the
| game is that you're going into it without a plan. I'm not
| judging, in your case maybe no-one is asking for any sort of
| accountability, and just executing is the best recourse with
| the lower overhead. But the fact that you can't estimate
| isn't due to the environment, it's due to the fact that you
| don't have a plan. Some of the companies I worked with are
| fine with that, most are not.
| strife25 wrote:
| When new scope is found, you update the plan of the project
| and provide new estimates.
|
| I don't expect my team to know everything about a project on
| day 1. I just want them to know enough to start and provide a
| "good enough" estimate.
|
| I do expect my team's estimate to get more accurate the
| further they get into a project.
| kqr wrote:
| Strongly seconding this. For anyone still hesitant, I further
| recommend the following experiments:
|
| ----
|
| Sample a few activities your team has completed. Check how long
| the 90 % smallest activities are on average, and compare it to
| the average of the biggest 10 %. Or the median compared to the
| maximum, or whatever. You'll probably find the difference is
| about an order of magnitude or less. In the grand scheme of
| things, every activity is the same size. You can estimate it as
| exp(mean(log(size)) and be within an order of magnitude almost
| every time.
|
| Once your team has accepted that something is "an" activity and
| not a set of activities, don't bother estimating. For all
| practical intents, size is effectively constant at that point.
| What matters is flow, not size.
|
| ----
|
| For the above sample, also study how long passed between the
| "go" decision on the task and when it was actually released to
| customers. In a stable team, this number will be eerily close
| to the theoretical based on Little's law referenced in the
| parent comment.
|
| Oh, and you shouldn't focus on man-hours. Work with calendar
| days. Not only does that simplify mental arithmetic for
| everyone, it's also the only thing that matters in the end.
| Your customer couldn't care less that you finished their
| functionality in "only" 6 man-hours if it took you six weeks to
| get it through your internal processes.
|
| ----
|
| Fun follow-up to the size experiment: now ask someone
| intimately familiar with your customers to estimate the dollar
| value of each activity. You might find that while all
| activities are practically the same size, they'll have _very_
| different dollar values. _That 's_ what you ought to be
| estimating.
| maigret wrote:
| This. I've found that, whatever the project is, the velocity
| of a team in terms what they define as a "task" is pretty
| constant, surprisingly so even. In the end, just counting the
| outstanding tasks proved to be a good estimator of where we'd
| end up at the deadline.
| codemac wrote:
| This is great for a simple monte carlo simulation!
|
| Choose a finished tasks time randomly, once per remaining task
| in the queue, and add this up to be a single estimate. Do this
| 1000 times or so and get an estimated distribution of
| completion times for the current queue.
|
| This type of thing is covered extensively in Evidence Based
| Scheduling[0], and is one of the reasons I still think FogBugz
| ' power is misunderstood.
|
| [0]: https://www.joelonsoftware.com/2007/10/26/evidence-based-
| sch...
| lelandfe wrote:
| Nice, I just recently left a company where this approach
| would have been tremendously useful and fairly easy to build
| - we had all the required data already, but were just looking
| at averages of past performance to budgets and using that as
| a multiplier on the schedule rather than going through a
| distribution.
|
| That being said, I also despise tracking time!
|
| ...Suppose you could move that technique to story points (or
| whatever unit of measurement) though you would lose a ton of
| precision.
| quickthrower2 wrote:
| New problem: can you estimate the number of queueable tasks in
| this supertask?
| qznc wrote:
| That is essentially what a Burndown Chart does in visual way,
| isn't it?
|
| https://en.m.wikipedia.org/wiki/Burn_down_chart
| twelfthnight wrote:
| This is interesting. A lot of machine learning works exactly
| like this [1], in the sense that you're biasing your prediction
| of each ticket time towards the average, except when there is
| strong evidence that ticket is special.
|
| (You'd arrive at exactly this method if you found that there
| were no easy to find characteristics of tickets that could
| distinguish them as extra-long or extra-short)
|
| [1] https://en.wikipedia.org/wiki/Ridge_regression
| siddboots wrote:
| A more "back of the envelope" approach to handling uncertainty
| for this sort of thing is the "three point estimate" approach,
| where you give a best, worst, and most likely estimate for each
| sub task. These points are implicitly used to parametrise a
| distribution, and then you analytically find the overall
| uncertainty, rather than through simulation.
| sethammons wrote:
| We used a different three point system. 1 point means we know
| exactly how to accomplish this work. 2 means there is
| uncertainty, but we are confident it will completed. 3 means
| there are unknowns that require more digging. A 3 pointer is a
| good candidate for breaking the story/task up into smaller
| chunks.
| DavidPeiffer wrote:
| While a different application than shown here, my project
| management class taught me one of the biggest benefits of Monte
| Carlo simulation - estimating uncertainty.
|
| Traditionally, net present value calculations are done with
| single point estimates. For example, analyzing a rental property
| we want to buy, we'd estimate the vacancy rate, interest rate,
| property appreciation, maintenance expenses, and do all of that
| on a cash flow time-adjusted basis.
|
| There's variability on every aspect of the through, and
| understanding how much can easily swing your decision.
|
| Traditional methodology is to pull the trigger on the action if
| the net present value is greater than 0. We put in a variety of
| estimated factors, ran it through Crystal Ball (simulation
| software), and found a 75% chance the NPV would be negative. It
| suddenly isn't the safe investment it looked like originally.
|
| ---
|
| In practice, it's tough to get people in business to understand
| uncertainty. They gravitate towards "the number", which is almost
| surely wrong all the time.
| nanis wrote:
| > Monte Carlo simulation - estimating uncertainty.
|
| By definition, "uncertainty" is the thing that does not have a
| PDF ... You can quantify risk based on assumptions you make
| about underlying probability distributions from which you are
| drawing. Far too often, even in Monte Carlo, people decide to
| work with the easy distributions instead of the most
| appropriate distributions.
|
| The "easy" distributions tend to admit actual mathematical
| solutions which means Monte Carlo is helpful if you can't do
| the math but not strictly necessary.
|
| Monte Carlo shines when you cannot get nice solution and there
| is your opportunity to not be constrained by the need to do so:
| Draw from appropriate distributions.
|
| Also, know the difference between LLN and CLT and when to
| appeal to which to justify your methods.
| mateo411 wrote:
| I would think that you could have "uncertainty" even if you
| do have a PDF. Maybe there is a formal definition of
| uncertainty that I am not aware of. The PDF can describe the
| uncertainty for every outcome.
| nanis wrote:
| Risk is what you can put a probability on (i.e., quantify).
| Uncertainty is what you can't. Uncertainty encompasses
| unknown unknowns. See Knight[1] and Keynes[2].
|
| Good rule of thumb even if it sounds overly simplified.
|
| [1]: https://www.econlib.org/library/Knight/knRUP.html
|
| [2]: https://www.jstor.org/stable/4538116
| JabavuAdams wrote:
| But ... but ... everyone knows that Nature is linear and
| Gaussian. Shhhh.
| IshKebab wrote:
| It's not just business people. I have yet to find a task
| tracking system (Jira etc.) that lets you assign a _range_ of
| points to a task.
|
| People try and use nonsense like Fibonacci numbers to imply
| uncertainty, but then just add up all the numbers to get a
| number with no uncertainty measure.
| jon-wood wrote:
| Story points are a curse on the software development
| industry. However much people say "they're indicative, and
| don't map to hours", someone, somewhere, will map them to
| hours.
|
| The most accurate project plan I was ever involved in had
| only 3 values that could be assigned to a piece of work
| during the early estimation phase: hours, days, and weeks.
| Each of those was then turned into a range of possible hours
| they could represent, with that range expanding as you got
| into larger units. You could then slice and dice the numbers
| however you choose to get anywhere between the most
| pessimistic timeline to the most optimistic timeline.
| Probably unsurprisingly the project was delivered somewhere
| between the two.
| IshKebab wrote:
| That seems reasonable, but I would say you don't have to
| resort to such crudeness. In my experience I know the
| difference between a task that will definitely take weeks
| and a task that might take a day or might take weeks. Just
| let me write that down!
|
| Even if you don't have any idea about the uncertainty we
| already have a crude way of measuring it - planning poker!
| Just record everyone's guesses instead of throwing away the
| uncertainty information. There's a huge difference between
| everyone guessing 5, and some people guessing 1 and others
| guessing 20.
|
| I agree about points being stupid though - there's simply
| no way to avoid it being converted to/from time, because
| that's the actual unit of work.
| jon-wood wrote:
| Sorry, reading back I definitely come across as
| disagreeing - I would kill someone for task tracking
| software which supports giving the degree of uncertainty
| on an estimate.
| Ntrails wrote:
| The real danger is not understanding that this "uncertainty"
| estimate is a function of your assumptions. How you model the
| distribution of your inputs is huge, and often not stated
| clearly.
|
| GIGO
| Loic wrote:
| GIGO, the first thing I learnt, as I entered the industry 20
| years ago. This was from a 60 year old engineer who told me
| that experience is only a nice name for "all the @#$% I made
| I will try not to make again".
|
| A very nice thing about Monte Carlo simulation is that at the
| end your distribution of results are all within the feasible
| range. If you do error propagation using uncertainty on your
| parameters, you can get non-sense results.
|
| For example, suppose you have a pendulum, you simulate it
| with error propagation and you have a non 0 probability of
| having an increase of the energy in the system over time.
|
| It is easy to _spot_ this in such constrained example but
| with more complex models, this is sometimes pretty hard to
| control.
| nuerow wrote:
| > A very nice thing about Monte Carlo simulation is that at
| the end your distribution of results are all within the
| feasible range.
|
| I guess Monte Carlo helps provide conservative estimates
| behind a facade of rigour, but the truth of the matter is
| that in the end it's still GIGO.
|
| Any empirical distribution only reflects the empirical
| measures that were used to generate it. If you bundle
| everything from the time it took employee A to walk the dog
| while allocated to project Foo to the time it took employee
| Z to fix a nasty Eisenbug while allocated to project Bar,
| and Foo and Bar used totally different tech stacks and team
| members and even approaches to project planning, that
| distribution is meaningless in estimating, say, how much
| time it will take employee G to implement a React widget.
| tonyarkles wrote:
| I'm smiling a bit while reading your comment. You are
| completely correct that that estimate is virtually
| meaningless. And yet... that doesn't mean it's completely
| useless!
|
| I've been using a somewhat meaningless Monto Carlo
| inspired approach to project planning for a while in my
| consulting company. The vast majority of the projects I
| do have only a small amount in common with previous
| projects, so when I'm estimating I'm informed by past
| estimate vs actual numbers, but not really relying on
| much other than intuition and gut feelings from past
| work.
|
| My basic approach is to estimate 2- or 3-sigma
| upper/lower estimates for each task, modelled
| (incorrectly) as a Normal distribution _in hours_ , and
| then sum the random variables to come up with a final
| distribution (whose variance is quite a bit smaller than
| what you see on the original bag of tasks). From there,
| if I am making a quote, I'll quote at +3-sigma x hourly
| rate as a high-end effort estimate. If it seems like a
| very meeting-heavy client, I'll either add meetings in as
| development tasks or just pad it out by a %age or fixed
| hours/week.
|
| This technique has worked amazingly well for me, and it's
| been quite rare that I blow the estimate, and in the...
| one time I can think of, we missed by very little and
| there were tasks that we hadn't thought of when we did
| the estimate.
|
| To your point though (with walking the dog), there's a
| really key thing that this process doesn't capture,
| somewhat on purpose: the resulting estimate is in effort-
| hours, not delivery date. While modelling per-task effort
| hours as Normal is suspect, modelling task delivery dates
| as Normal is completely irrecoverably wrong: delivery
| dates, in my experience, only ever slide in one
| direction. People get sick and the project slips a week;
| people don't ever get super healthy and effectively knock
| out 80 or 120 hours worth of tasks in a week.
|
| I honestly haven't found a good way to estimate delivery
| dates very well. At one point I did put together some
| regression on my "actual billed hours per week" based on
| my billing, but ran into the same problem. "Oh, my dog
| died and my mother-in-law got sick during that project."
|
| Someone who's better at statistics might have a better
| way to model that as a high-skew distribution, but when I
| tried doing that myself I ended up with a distribution
| that didn't feel like it did a good job of capturing the
| non-negligible long tail of things that slow down
| calendar estimates without burning hours.
| jacques_chester wrote:
| The traditional distribution for costs and dates is Beta-
| PERT. Douglas W. Hubbard uses log-normal distribution. I
| am a pessimist, so I like Beta-PERT with a fat, fat tail.
| conjectures wrote:
| > If you do error propagation using uncertainty on your
| parameters, you can get non-sense results.
|
| Only if you do it wrong, generally. Events which are
| impossible under some hypothesis should have zero
| probability under a model for it and not be sampled.
| ChrisMarshallNY wrote:
| _> experience is only a nice name for "all the @#$% I made
| I will try not to make again"_
|
| One of my favorite quotes is one that was made famous by
| Will Rogers and Rita Mae Brown:
|
| _" Good judgment comes from experience. Experience comes
| from bad judgment."_
|
| I have seen this "attributed to Nasrudin," which means no
| one really knows who came up with it, the first time.
| dotancohen wrote:
| > The real danger is not understanding that this >
| "uncertainty" estimate is a function of your assumptions.
|
| The bigger danger, in my experience, is treating _estimates_
| as _deadlines_.
|
| Unfortunately, that seems to be the norm in almost every
| place that I'm familiar with.
| Mtinie wrote:
| "Don't worry, this is _purely_ an estimate and would never
| be used to set the deadline. So just give us something to
| share with the ELT..."
| mgkimsal wrote:
| "Just take a guess - we have to have a number in this box
| by the end of the meeting". I was literally just told
| that yesterday. No one else who would look at that number
| will know it was a totally random guess pulled out of
| thin air to satisfy ceremonial box-filling. They will
| treat it as an estimate, and make plans accordingly.
| cratermoon wrote:
| And if you make up a number that is too obviously small
| or exceeds some unspoken upper bound, you'll be asked to
| re-estimate anyway. Sometimes the best way to respond to
| that is to finesse the discussion into coming up with a
| number that, while it will have no relationship to the
| actual effort, at least reflects what the stakeholders
| hope and desire it to be. At that point the team, if they
| are smart, will examine scope and re-plan to come up with
| some level of effort that they are confident can be done
| in the time hoped for.
|
| In other words, get the people who want a number to tell
| you what number they want, then use your best efforts to
| scope the effort to one you can be pretty confident will
| fit.
| tchalla wrote:
| One of the concepts that many people don't get is
| differentiation between risk and uncertainty. These same people
| will then attempt to "model risk" and end up with (ironically)
| an "uncertain estimate"
|
| https://en.m.wikipedia.org/wiki/Knightian_uncertainty
| potatoman22 wrote:
| They define risk as having statistical noise or a varying
| parameter in the estimate, while uncertainty is lacking
| information about the target. Doesn't the presence of noise
| in an estimate imply that there's information you aren't
| accounting for? I don't see the importance of the
| distinction.
| m12k wrote:
| Estimating uncertainty is preferred, but if you have people who
| insist on a single number, then teach them that it should be
| the median instead of the mean. Means tend to overvalue
| "moonshots" where there's a 99% chance you lose money, but if
| the payoff in that 1% where you win is large enough, it can
| still result in a positive mean. And a mean can often be an
| outcome that isn't actually possible, but falls between several
| options, while a median is always an outcome that can actually
| happen, and there's ~50% chance you'll get a better one.
| tonyarkles wrote:
| Heh, when people ask for a single number estimate, I give
| them mu + 3-sigma. If you're curious, I've got a sibling
| comment that describes a bit more.
| mjburgess wrote:
| A related field:
| https://en.wikipedia.org/wiki/Real_options_valuation
|
| > This simple example shows how the net present value may lead
| the firm to take unnecessary risk, which could be prevented by
| real options valuation.
|
| Even with a monte carlo on NPV, you may still make a more risky
| decision than needed; as decisions are rarely just "do or dont"
| but can be sequenced pending more information.
| another-dave wrote:
| I'd love to hear a post mortem blog post on a project that was
| ran in this way in real life & what the pros/cons at different
| stages were.
|
| The author first talks about the waste of time that is upfront
| analysis/planning or adding a buffer for contingency and how
| Monte Carlo simulation fixes for that, but then the caveats seem
| to be based on an established team, of a fixed size doing similar
| style work.
|
| For me, this stage of a project has never faced big hiccups in
| estimation & our teams are normally quite good at knowing "what's
| a 2 vs a 5 point story" -- if there _is_ a big discussion in a
| planning meeting at that stage, it's normally because one person
| has overlooked a key requirement (or the other is assuming a
| requirement that doesn't exist) so it's a good opportunity to
| solve for that.
|
| To use the analogy, we're probably quite good in established
| teams at estimating how long it'll take to write 10 blog posts.
| The trouble comes when someone says "The latest blog posts aren't
| generating enough interest. Can you estimate how long it'd take
| for you to write 10 poems instead? We want a mix of iambic
| pentameter and maybe some trochaic tetrameter (TBC). We've gotten
| budget approval to increase the size of the team, so we'll have 5
| new people (off-shore) joining next week so we can go faster.
| Also, some of the old blog posts seem to be getting lots of
| visitors in South America, so we may need to translate these to
| Portuguese/Spanish too. When can you give me an estimate for all
| that?"
| srparish wrote:
| The book "How to Measure Anything" by Douglas W. Hubbard has a
| chapter on using Monte Carlo simulations to do project planning
| and gather estimates. It's successfully been used for project
| planning large complex projects like building nuclear power
| plants, or projects that NASA or the Navy or similar have done.
|
| The approach is slightly different then the article above
| describes. Instead it has each engineer go through calibration
| exercises until they can fairly accurately produce 5th and 95th
| confidence interval estimates. Then each engineer provides 5th
| and 95th confidence interval estimates for each item that needs
| to be worked on. Those confidence intervals are kept separate.
| You can then run a Monte Carlo simulation where each piece of
| work is weighted randomly assigned to each engineer that
| provided estimates for that particular item, and randomly picks
| a number based off their provided confidence interval estimate
| on how long it ends up taking them to complete the item for
| this particular simulation.
|
| I was on a small team that used the above technique. We were in
| a large company trying to launch a new product, and given
| manufacturing lead time, and seasonality of the market demand,
| it was very important that we could provide a good estimate to
| the business when we could have the software portion of the MVP
| completed. The business provided us with what they thought the
| MVP features were, we further added in engineering tasks that
| weren't business facing, but needed to be completed. We
| confidence interval estimated those, and then also confidence
| interval estimated our personal vacation days, sick days, as
| well as a bucket of "unidentified work". The 80th percentile
| Monte Carlo simulation put us out a little more then a year.
| Our actual delivery was off by only a week from the Monte Carlo
| tp80; I don't remember in which direction, but it wasn't
| consequential to the business.
| hbarka wrote:
| Has anyone used Excel's Monte Carlo Simulation? I believe they've
| had it since Excel 1999.
| rightbyte wrote:
| How is this different to just summing estimated value and
| variance?
|
| I agree with the author that agile world zero effort estimates
| are pointless though.
|
| "... engineers determine it by licking the tip of their finger
| and putting it up in the air.
|
| Unfortunately, the only way to win at the estimation game is not
| to play it." "
| qubex wrote:
| For anybody who wants to try it out in a spreadsheet environment
| and/or is looking for a useful abandoned project to duplicate, I
| recommend Risk Engine for Mac. Unfortunately it hasn't been
| maintained for a long time and has been abandoned, but I keep
| using it.
|
| https://www.macupdate.com/app/mac/30431/risk-engine
| mirekrusin wrote:
| It's fascinating how poor this area currently is. We are able to
| capture so many tiny, horrifying details about engagement and
| optimise shit out of ad clicking but we don't do basic things
| like using calendar or task dependency for internal delivery
| estimation.
|
| Looking at what we're already doing on outside, improvements
| inside seem trivial. Good estimator should know that estimation
| spanning holiday season will be impacted. It should know serial
| dependency will span wider in time. It should know that set of
| unevenly distributed tasks (A-many + B-not-many) for small-team-A
| and larger-team-B will flow slower in time than distribution
| matching weighted max flow for team A and B. It should know
| multiple dependency on team X will have lower flow because
| they're maxed out.
|
| It seems to me that monte carlo projection on timeline from
| inputs we already have mapped onto graph is really not a rocket
| science and it should have been solved problem by now. But it's
| not. Weird.
| smallnamespace wrote:
| Now you need to guess the variance and correlation between
| events, and if you get it badly wrong it ends up like CDOs in '08
| shapefrog wrote:
| Let the observed data do the work and remove the guessing by
| use pairs / trebbles etc. of past events in your simulation.
| FredPret wrote:
| Speaking purely to Monte Carlo simulations: one key issue is
| knowing the underlying distributions of your random variables.
| Without this, you may be led further astray than before your
| simulation.
|
| A much more robust approach - though not always appropriate - is
| a worst-case vs middle vs best-case scenario analysis
| diiq wrote:
| If you don't want to script your own, Vistimo Quotes lets you do
| monte-carlo simulation with vague, uncertain estimates; and lets
| you play with variables like the number of people working,
| vacation time, etc.
|
| https://quotes.vistimo.com
| ImaCake wrote:
| A little bit of knowledge about stats and the appropiate language
| helps make this exercise easier. The R language is good at this
| kind of simulation. It comes with a whole bunch of random number
| generators out of the box. Here is how to estimate frequency of 7
| from sums of two d6 dice rolls in R in two lines:
|
| n <- 1e06
|
| table(round(runif(n,1,6))+round(runif(n,1,6)))[6]/n
|
| To break this down:
|
| `n <- 1e06` assigns 1 million to n.
|
| We want two six sided dice so we sample a random uniform
| (continous) distribution and round to a whole number:
|
| `round(runif(n,1,6))`
|
| This will make a vector of 1 million integers representing random
| "rolls" of the dice. In R it is really easy to pair-wise add two
| vectors of the same length so to get two dice we do:
|
| `round(runif(n,1,6))+round(runif(n,1,6))`
|
| Now we have a million rolls of summed pairs of dice. We want the
| frequency count of 7s. We can get this by getting the frequency
| count of every dice with `table()`:
|
| `table(round(runif(n,1,6))+round(runif(n,1,6)))`
|
| Which will return a print out of frequencies for every number
| that appears in the vector.
|
| We can select 7s by pulling the 6th index and then dividing by
| the `n` dice rolls to get the frequency:
|
| `table(round(runif(n,1,6))+round(runif(n,1,6)))[6]/n`
|
| We can do the exact same oneliner in python using numpy and the
| Counter() function from collections:
|
| `Counter(np.around(np.random.uniform(1,6,size=10*6))+np.around(np
| .random.uniform(1,6,size=10*6)))[7]/10*6`
|
| Will return the frequency of 7s in python3.
| BOIServices wrote:
| Get hassle-free permanent residency in Canada with BOI Services.
| Choose express entry, PNP, pilot programs in Canada. Easy and
| fast immigration for Canada PR. https://www.boi-
| services.com/permanent-residency-in-canada
| xyzelement wrote:
| Many commenters on this story believe the main purpose of
| estimation is to assert when something will be done. Then they
| say "this is impossible" and call the whole exercise a waste of
| time, or management abuse.
|
| I gotta tell you that unless you're working with absolute bozos,
| nobody is looking at estimates and saying "oh duh, I am betting
| the farm this will complete on that date."
|
| Benefits of estimation that are more important that the date
| itself:
|
| Enabling trade-off analysis: If you tell me the thing will be
| done in two months, I bucket the thing in my head as something
| that takes "a few months" as opposed to "weeks" or "years." Often
| that is enough to drive a build/pass decision on the feature.
|
| Dependency visualization: If I don't ask you to estimate, you
| might just start coding. Estimation may force you to think about
| critical paths and dependencies, then we can plan for them to
| improve your chances of success.
|
| Troubleshooting: why did we miss an estimate? A task was harder
| than we thought, that's ok. We missed a dependency, ok that's a
| prompt to think about those better next time. Developer keeps
| getting distracted, maybe we need to change something on the
| team. Estimation is just "calling a shot" which then enables us
| to (maybe) learn from missing it.
|
| All those things are valuable even if the actual estimated date
| is missed, even by a lot.
| toss1 wrote:
| >>I gotta tell you that unless you're working with absolute
| bozos, nobody is looking at estimates and saying "oh duh, I am
| betting the farm this will complete on that date."
|
| I hate to break it to you, but it happens a lot (and yes,
| management structures can often work to filter absolute bozos
| upwards). They make all kinds of representations to customers,
| investors, etc. about dates that have nothing approaching this
| level of estimation, more of a wishful-thinking goal. And when
| they fail, investments, customers, jobs, and even companies are
| lost -- often unnecessarily if better plans and contingency
| plans had been made.
|
| Sadly, just because it is blindingly obvious to you and me,
| does not mean it is so obvious to someone in a mgt chair.
| xyzelement wrote:
| Eh, I think there is two ways this can go.
|
| If you're really working with people who are 'so stupid' as
| to take estimates literally and make plans assuming
| guaranteed success in those times, then you probably have
| other leadership/management/risk problems in your company and
| are doomed anyway.
|
| There are plenty of time where there's a little bit of
| managerial art to communicating estimates to customers and
| prospects. For example, if my devs say "October, the API will
| be available", I may share that with the client _if_ I
| understand that in reality it will take the client a long
| time to actually start using that API in production. So I may
| say "Probably early November..." with the mutual
| understanding that that's when they'll _begin_ to integrate
| but the thing may not actually be prod-ready from either of
| our sides till January. It 's complicated!
| toss1 wrote:
| You are making the assumption that development estimates
| have anything to do with when management, sales, or
| customers decide that they need something.
|
| Even without mgt/sales over-promising stuff to customers
| based on wishful thinking and only wanting to say "Yes" to
| a stupid customer demand without even bothering to ask
| development/engineering, I've seen situations where the
| date is the date, period.
|
| I've been in plenty of situations where it doesn't matter -
| it's an event, scheduled years in advance, national
| television, and the show goes on at Monday 16:00 PDT,
| period. Scheduling estimates have nothing to do with it. Be
| ready and be there, or everyone gets nothing. The only
| question is: "Can the team do it?".
| brightball wrote:
| You get all of the benefits that you're looking for just by
| planning what needs to be done, estimations or not.
|
| You break down the tasks, the dependencies, the risks,
| complications, places where there are options that need more
| research or comparison...and you'll see the volume involved and
| have an idea of the size in the terms you mean. All without
| numerically estimating a single task in the plan.
| giovannibonetti wrote:
| > All without numerically estimating a single task in the
| plan.
|
| However, often you have multiple paths to achieve a goal, and
| you have to choose which one you're going to take. Either you
| estimate each path in days/weeks/months or you'll have to
| compare all the alternatives (a > b?, b > c?), at which point
| having numbers is probably worth it.
| mgkimsal wrote:
| > I gotta tell you that unless you're working with absolute
| bozos, nobody is looking at estimates and saying "oh duh, I am
| betting the farm this will complete on that date."
|
| Apparently I've worked with a lot of bozos over the last 25
| years... (apologies to everyone I've worked with).
| hinkley wrote:
| Lion tamer reporting in. It's all circuses out there.
| mumblemumble wrote:
| I would also argue that enabling capacity planning and drawing
| a boundary around the scope are also valuable by-products.
|
| Perfection may be impossible, but Brooks' Law being a harsh
| mistress, and scope creep being a very real thing, having a
| serious think about how big you intend the project to be to be
| _before_ you start can make the difference between finishing it
| in months, and having it turn into a years-long death march
| project.
| 8note wrote:
| Explicitly asking for a critical path sounds better than hoping
| somebody will consider it while doing something else.
| luckydata wrote:
| this is an incredibly obvious yet valuable comment but all the
| replies seem to be working hard to miss the point.
| dagw wrote:
| _I gotta tell you that unless you 're working with absolute
| bozos, nobody is looking at estimates and saying "oh duh, I am
| betting the farm this will complete on that date."_
|
| Happens all the time, and not just by bozos. Sometimes getting
| paid is entirely dependent on delivering when you said you
| would. I used to work at an animation studio and one year we
| worked on a series of Christmas themed TV spots. When we said
| we could deliver on time we where very much betting the farm
| our estimates where correct. Nobody is paying to air those in
| February.
| radicaldreamer wrote:
| Similar story, in a larger firm. There are internal
| incentives where teams are compared against each other and a
| lot of it hinges on delivering things when a team said it
| would.
|
| This leads to all sorts of strategies to make that happen:
| from cutting corners, to underpromising, to padding
| estimates. In the end, the sum of it all is that nobody is
| able to paint an accurate picture of the capabilities of
| teams overall because everything is so heavily skewed by
| internal incentives and competition.
| listenallyall wrote:
| That's not an estimate, it's a deadline. Different concepts.
| cratermoon wrote:
| But they are bozos if they give you a task they want done for
| Christmas, you tell them that it will likely not complete
| until February, and they say, "well, just work harder/extra
| hours/hire more people", which is pretty common.
|
| The way to avoid bozo-land is for the person asking to come
| back with "well, what _can_ you confidently complete in time
| for Christmas? ", and plan for that.
| groby_b wrote:
| > I gotta tell you that unless you're working with absolute
| bozos, nobody is looking at estimates and saying "oh duh, I am
| betting the farm this will complete on that date."
|
| Meanwhile, anybody working anywhere close to the retail space
| fell laughing off their chair. Thanksgiving won't move no
| matter how much you insult your co-workers.
|
| (This is not limited to retail. Many industries have fixed
| delivery dates and bet on those. Thanksgiving is just the most
| obvious example of an immovable object)
| e12e wrote:
| There's a difference between "it's done now, _before_
| Thanksgiving, let 's bet the farm on it" and "it might be
| ready two days before Thanksgiving, let's bet the farm on
| _that_ "...
|
| Ed: that said, given gp quote about working with bozos,
| there's always that anecdote from the introduction of (2nd
| ed) of Peopleware, about the deadline being moved, because
| the project was on track for meeting the original deadline...
| (March meeting: we can deliver as planned in June - project
| leader called back; we've moved the deadline to April -
| paraphrased).
| HWR_14 wrote:
| If you supply anything that retail needs on Thanksgiving
| (including physical media containing digital assets), you
| have a very strict timeline as well. There is sometimes a
| possibility to pay extra to expedite a later part of the
| production process (ship via air instead of ship?) but that's
| still a big hit and often isn't even available.
| nanis wrote:
| While the article is rather low quality in and of itself, it
| still manages to point out:
|
| > Before claiming that the simulation above is reliable, I must
| expose a few things you'll need to pay attention to when using
| a Monte Carlo Simulation to make forecasts:
|
| > (A) The quality of the inputs upon which your simulations
| depend.
|
| > (B) The consistency and predictability of your team.
|
| > (C) The need to re-forecast.
|
| > (D) The size of your work packages.
|
| Among those, I am not exactly sure what the author is referring
| to with (C). However, problems arise most often when none of A,
| B, and D is controlled by the person being asked to estimate.
|
| Now, if you can control A, B, and D, YOU DO NOT NEED TO RUN
| MONTE CARLO. You'll be able to split the work and guess within
| 10 - 20% just by using rules of thumb.
|
| If you cannot control A, B, and D, running Monte Carlo will not
| help you.
|
| I say this as a person who's been doing Monte Carlo since the
| late 80s.
| canadianfella wrote:
| > in and of itself
|
| What's the point of adding these words?
| alangibson wrote:
| > I gotta tell you that unless you're working with absolute
| bozos, nobody is looking at estimates and saying "oh duh, I am
| betting the farm this will complete on that date."
|
| I gotta tell you, you've never worked with a business
| stakeholder, the government (see financial penalties for
| missing deadlines) or with an absolute deadline (ie Christmas)
| if you think that's true.
|
| > Many commenters on this story believe the main purpose of
| estimation is to assert when something will be done
|
| We know our estimates can never be guarantees, but that is
| irrelevant to stakeholders whose career advancement depends on
| project X being done in day Y. Guess who's opinion carries more
| weight in literally every profit making enterprise.
| xyzelement wrote:
| You and a few other responses hit on a related but distinct
| problem: an unmovable deadline.
|
| In this case, the question is no longer "how long will X
| take" but "but what will it take for X to complete by Y."
| That can require aggressively cutting scope, reassigning
| resources, de-risking in every possible way. That's quite
| different than asking a developer/team "how long this will
| take" assuming constant resources and given scope.
| digikata wrote:
| There is a reason project management calls scope-cost-time
| the iron triangle. It's extremely to bind all three sides
| tightly unless the estimates are very good, and/or there is
| significant added buffer to the project (and that really
| means the cost side is what's stretching to give you extra
| certainty on the hard scope and time deadlines).
|
| More commonly at most two of the three are tightly
| constrained, and another side is more free. One can optimize
| in some directions, but none of the sides are fully
| independent of each other. I think the best project outcomes
| I've seen on are ones where only one side is strongly fixed,
| and the team is in control of the other two aspects.
| zackmorris wrote:
| I wish we had public Monte Carlo simulations for the economy.
|
| It's hard watching people argue about things with almost no
| evidence. The cynic in me is starting to think that that's all
| politics is. But imagine if people did have evidence, or at least
| projections within an error bound like the roughly 3% margin of
| error for polls, and could make decisions based on likely
| outcomes.
|
| For example, how much would taxes on the US middle class decrease
| if taxes on the wealthy were raised? How much lower would they be
| after 5 years, 10 years, if that excess capital was reinvested
| in, say, an automation moonshot? I've framed a scenario which is
| obvious to me after running the simulations in my mind over 40
| years of watching the national debt increase, but maybe I'm wrong
| (unlikely).
|
| This site has a "Sample Size Calculator" tab which has a
| calculator for the number of samples needed to reach a certain
| confidence level:
|
| https://www.pollfish.com/margin-of-error-calculator/
|
| More info:
|
| https://en.wikipedia.org/wiki/Margin_of_error
|
| For a population size of 350 million, to get to a 95% confidence
| level with a 3% margin of error, requires polling 1068 people.
| Getting to 99% only requires 1849 people.
|
| Now why can't we write something like the program from the
| article, maybe with some Bayesian inference, maybe some machine
| learning, with big sample sizes and high confidence levels? This
| may be the plot of some dystopian novel, but, surely more
| evidence would help inform a populace that's being spoon-fed
| ignorance by coopted media?
| benmanns wrote:
| There are, roughly speaking. You can look at option pricing to
| see market predictions on various outcomes, at least ones that
| can be boiled down to "what will the price of SPY/TLT/EURUSD be
| in 2022?" If you have a better simulation, take your output and
| trade against the market where it's wrong.
| alangibson wrote:
| I tried this at a past job. I fed Jira history into a Monte Carlo
| simulation that would give a set of probabilities for various
| completion timeframes for any new user story. Despite months of
| trying to sell the idea, backed by sound mathematics instead of
| guesses, I never got past the point where stakeholders would
| listen politely then immediately go back to demanding to know
| "when will it be done"
| jrek wrote:
| The issue I've always had with Monte Carl simulation in this
| context is that it takes more knowledge, expertise, time, and
| care to accurately perform a Monte Carlo Simulation than to
| prepare an accurate estimate. It's like saying you can avoid
| building (yet another) barely functional go-kart by instead
| building a four-wheel drive. Monte Carlo Simulation sometimes
| cloaks that the assumptions behind the simulation largely
| determine the output and are just as (if not more) prone to error
| as the usual assumptions.
|
| If the burden of accurately estimating an average duration for a
| blog post is too much for your planner, what are the odds they're
| going to accurately develop a probability distribution for the
| duration of a blog post?
|
| In simple estimates there's no need to use a stochastic approach
| at all. For instance, the example in the post - if you know a
| blog post takes between 1-10 days (uniformly distributed) and
| that you need to get one out every ~6 days to get 60 out in a
| year, you already know the probability is ~60%. If you know
| there's a skew to the higher end and guess a distribution (as in
| the example), again you can directly work out that the odds of
| success are ~35%.
|
| There is value when the estimate is not corrupted by other
| priorities (rare), when the expertise to accurately develop
| distributions for activities exists (also rare, particularly for
| work that isn't easy to sample and re-forecast), and when the
| plan is complex enough that it's hard to directly predict the
| impact of your statistical assumptions.
| atum47 wrote:
| I wrote a Monte Carlo area calculator once. Just draw an
| arbitrary shape and hit solve. You can increase the number of
| samples used.
|
| https://victorribeiro.com/monteCarlo/
|
| The drawing area is 500x500 pixels, so if the shape covers the
| whole area, the result should be 250.000 pixels
| triggercut wrote:
| Whilst I'm happy that probabilistic methods of estimation get air
| time, I feel these sorts of posts give the lay person unearned
| confidence that they are suddenly far safer then they are. In
| most cases I find people don't know what should be planned, how
| it should be defined, measured, tracked or assured - and when
| combined with a lack of appreciation for Risk and how it should
| equally be defined, measured, tracked and controlled this is the
| core problem not idea of estimating itself.
|
| ### Skip to TLDR ###
|
| Usually it's of little consequence and the stakes are low, but
| it's this general lack of skill in such a large population of
| people who are doing it poorly that gives estimation such a bad
| reputation in the first place. The idea of estimation is not
| incorrect, it's that people aren't taught how to do it properly
| in the first place and industry continues to propagate the myth
| that it's simpler than it is. Often because it's mandated by
| those who don't understand it themselves.
|
| Having played in many types of industries I have a thesis that
| much of what we do in planning and estimating has had real
| benefit in some areas historically - where there are clear,
| repeatable, measurable observations, certain types of
| construction and fabrication - but not others due to their
| success being tied to the method alone without account for how
| the nature of what is being measured.
|
| Monte Carlo has very real and valuable uses in critical path
| method scheduling, but, as with _most things_ , only when used
| appropriately. Weather is something that fits well, because it is
| cyclic, we have a lot of data, we can, ahead of time, to some
| degree, have a likely view of where and when things like
| hurricanes/cyclones will occur in a given period.
|
| In the Australian North-West Shelf where I used to plan O&G
| maintenance dive campaigns, knowing how long it takes to get to
| an area, a diver to get to depth, perform a task, return safely
| and leave the area is the easy part. "Everything going to plan"*
| we should be able to do these x number of
| inspections/interventions in y number of days. But weather is
| where you can come unstuck. Sea state matters, there is always
| some chance that you will have to interrupt or postpone on a day
| because of conditions. We know there are roughly x number of
| these days per cyclone season and roughly how long we might not
| be able to work for but pay full rates for crew, equipment etc..
| An at risk period for weather goes on to the end of the schedule
| as contingency and is drawn down as needed, but in some scenarios
| _where_ in the network of activities these multi-day events occur
| can have varying impacts. Inserting a three day stand-down early
| on could have a greater impact on the end date than a three day
| stand-down right near the end if at the earlier time you are
| doing things that must be done in a continuous sequence with - if
| interrupted - will need you to repeat again from the beginning.
| Luckily there are tools we can use to not just look at the net
| effects of activities in a schedule network having their own
| distribution curves, but also injecting events, again with their
| own probabilities, randomly throughout the network during the
| run.
|
| This gives you a much greater insight than a 'P90' estimate on
| your critical path, it gives you the sensitivity of activities in
| your network.
|
| ### TLDR ###
|
| This all assumes, of course, that what you have modelled
| (planned) reflects reality to some degree. A bad schedule with
| bad bounds will give you a bad result regardless. It doesn't
| matter how many times you simulate it.
|
| *it rarely does
| emrah wrote:
| I think FogBugz used this method to estimate how long open
| tickets would take to get closed. Or at least I remember Joel
| talking about it. I wonder if there are any other issues tracking
| apps out there making use of this technique
| saithound wrote:
| Yeah, FogBugz had a very similar feature 15 years ago.
|
| It was a hybrid between the approach proposed in the article,
| and the "always multiply by N" technique.
|
| Basically, FogBugz always asked you for your own best estimate.
| It tracked how much longer the actual time to completion was
| compared to your best estimate, and learned a simplified
| statistical distribution of your personal multipliers (e.g. in
| 80% of cases your estimate was 20% shorter than actual time to
| completion, in the remaining 20% of cases it was 10% longer).
|
| FogBugz used the learned distribution to perform Monte Carlo
| simulations, and presented you with estimates of actual time to
| completion (e.g. "in 95% of simulations the project didn't take
| longer than 30 work days"). The great thing about this method
| is that it automatically accounts for chronic optimists, who
| always think it'll be ready to ship soon, and underestimate
| difficulty. The learned multipliers tell the algorithm that the
| estimates made by the optimist tend to be underestimates, so
| that it can present you with a "debiased" estimates.
|
| E.g. if something always takes at least twice as long as
| Developer Anderson says it will, then FogBugz would tell you:
| "Anderson estimated 10 days, but based on past data I think
| it'll take at least 20, and it took less than 15 only in 5% of
| the simulations".
|
| It had a very simple algorithm at its core, but the developers
| were knowledgable ,and had tons of data about project
| management. This allowed them to add many empirically verified
| "embellishments" (e.g. if the algorithm didn't have enough data
| about your specific multipliers, it assumed that your
| multipliers were about the average of your coworkers'), which
| made the algorithm surprisingly accurate in the end. Certainly
| better than any estimates most people could produce by hand.
| adrianmsmith wrote:
| I never tried FogBugz but I heard good things about it,
| similar to what you've written. It's surprising it didn't
| catch on more if it's that good? I mean, I suppose it could
| still catch on, the product still exists as far as I know.
| gecko wrote:
| I've written about why FogBugz failed before, but it
| basically came down to Atlassian having vastly better
| marketing, being much more willing to support every edge
| case instead of being opinionated, and having a better
| pricing model.
|
| Unrelated, the new owners of Kiln and FogBugz are asshats,
| I moved my stuff off ages ago, and I'd encourage anyone
| else still on them to do the same.
| da39a3ee wrote:
| > let die = Uniform::from(1..7);
|
| I think this is a good example of the bad consequences of zero-
| based indexing. First, I hope you agree that a line of code
| describing a six-sided die should never feature a literal 7!
|
| But zero-based indexing causes us to embrace exclusive ranges: if
| we want 6 numbers, we write 0..6 and that's fine.
|
| If you want 6 numbers starting at 1, then you must use an
| inclusive range operator, since you don't want to bring the
| irrelevant number 7 into the picture. Now Rust has that: ..= and
| the author should use it here. But e.g. Python does not.
| Personally in Python, I would still refuse to write 7 and write
| range(1, 6+1) instead, but that's most people would write range
| (1, 7).
|
| Which brings me to my point: I'm not trying to argue against
| zero-based indexing, but I believe that
|
| (a) programming language designers (e.g. Python) don't recognize
| sufficiently that it has downsides as well as upsides, and
| languages need to provide things like inclusive ranges, even if
| they don't actually provide 1-based indexing, since 1-based
| indexing scenarios do naturally occur when programming. It seems
| that Julia is an example of a language that has very much
| recognized that both sides have merit.
|
| (b) In the standard case of a language that basically adopts
| zero-based indexing (most modern languages), 1-based thinking
| should not be presented as somehow vulgar or ignorant. A good
| test of whether your language is too hardline on zero-based
| indexing is: would you ever see users of your language using the
| literal 7 when describing a six-sided die? If you see that
| happening, the language is being too hardline on zero-based
| indexing; either you don't provide inclusive ranges or they're
| not promoted enough in the documentation.
| peter_retief wrote:
| Code used Rust, interesting, I have come to expect Python and
| just recently used the open source version of Matlab called
| Octave.
| lucasfcosta wrote:
| Author here. I thought no one was going to make comments about
| Rust, but I just loved using it for this post.
|
| Thanks, Peter :)
| peter_retief wrote:
| I have been looking for an excuse to use Rust, thank you for
| the interesting post on all counts...
| staplung wrote:
| Rust is cool and all but I feel like the code examples would
| have been a bit more didactic in e.g. Julia since there's
| less distracting complexity in those types of languages.
| Here's a somewhat equivalent translation of the first
| snippet: rolls = 1_000_000 n_sides = 6
| sevens = 0 for _ in 1:rolls if
| rand(1:n_sides) + rand(1:n_sides) == 7 sevens
| += 1 end end println(sevens/rolls *
| 100)
| ruste wrote:
| I've actually been working on turning this idea into a product
| for the past year or two. Looks like I'm not the only one to have
| thought of this!
| jacques_chester wrote:
| I worked on something similar a while ago. I was defeated by UX
| more than the mathematics.
| rainworld wrote:
| An example of that: https://arxiv.org/abs/1806.02404
| vgeek wrote:
| Monte Carlo simulations are invaluable when it comes to creating
| tissue line odds. For one of my horse racing projects, I can come
| up with a range of how an individual horse is likely to perform--
| which isn't much use unless compared against the others in the
| race with a frequency component (e.g., this horse will likely be
| the best only 10% of the time-- but the pools are offering 15-1
| odds, so it is +EV). On modest hardware, I can run thousands of
| race simulations and somewhat effectively determine the
| likelihood of a given horse winning.
| xornox wrote:
| After many decades we still discuss and wonder how work amount
| estimates should be done and why they are always wrong. The most
| brilliant software engineers and project managers have developed
| countless different methods and nothing works.
|
| For me it tells that nature of work is such that we just can not
| estimate work amounts. We are just pretending that it can be
| done.
| xarope wrote:
| Absolutely; we still treat knowledge-based work as if it were
| factory based with known inputs and outputs (someone can chime
| in on MBAs etc...)
| shapefrog wrote:
| Are you suggesting that MBA programmes are a factory with
| known inputs and outputs? Probably a fair critique
| mach1ne wrote:
| It depends on the type of work. Generally and
| counterintuitively, the more individual random variables the
| work contains the easier it is to estimate. This is because
| random variations cancel each other out when they are in large
| quantities.
|
| With programming, one random variable can add days, weeks or
| even months of work.
| myth2018 wrote:
| I think that one of the factors making it so difficult to produce
| accurate estimates on software projects is their usually high
| levels of variability. There are often so many big differences
| between projects and it's hard to consistently draw lessons from
| past experiences.
|
| However, it seems that when such variability is low, it gets
| easier to make predictions.
|
| I've seen an ERP company which used to provide good estimates for
| most of their customization projects. However, they used a home-
| built, suited-to-the-task programming language, the team was
| experienced and relatively stable, and the projects' scopes were
| usually narrow.
|
| Those factors are not easily reproducible, for sure. But I
| believe they indicate that taking measures to reduce variability
| and standardize processes may pay dividends in the long run --
| projects may take longer than they would take under agile
| approaches, but the improved predictability may be desirable.
| cratermoon wrote:
| I feel like the author just re-invented the XP concept of
| Velocity[1], but gave it a mathematical form.
|
| 1. https://martinfowler.com/bliki/XpVelocity.html "You should
| usually determine velocity by measuring how much got done in past
| periods, following the principle of YesterdaysWeather. A typical
| approach is to average the velocity the past three time periods
| to determine velocity for future time periods."
| myth2018 wrote:
| I think it's understandable why programmers dread doing estimates
| so much. But I believe there are multiple factors contributing to
| the current overall mess and the guilt should be shared among
| several areas -- and that includes us.
|
| Estimates are often, if not always, mistaken as commitments or
| deadlines. But we don't do a great job on explaining that
| estimates are probabilistic by nature, there are risks involved,
| and leaving those risks entirely to developers may be comforting
| at the beginning, but harmful to the entire Organization in the
| long term.
|
| Granted, that would be a huge cultural change, which surely is
| not going to happen overnight. Besides, political conditions are
| seldom in our favor. But I advocate that we should do the
| possible to dialogue.
| game_the0ry wrote:
| > Estimates are often, if not always, mistaken as commitments
| or deadlines
|
| This. This is _the_ problem with "estimates."
|
| My solution - and this will sound bad - is to over-estimate.
| mateo411 wrote:
| Yes, this is everyone's solution, all the way up the
| organizational hierarchy.
|
| Software Engineer, it will take me 2 weeks. Engineering
| Manager it will take us 4 weeks. Product Manager it will take
| them 8 weeks. VP it will be done by the end of next quarter.
| myth2018 wrote:
| I don't judge, and I recur to this solution as well, more
| often than I'd like to. But it doesn't only sounds bad.. it
| is bad indeed, for a number of reasons.
|
| For instance, work usually expands to spend all the time
| available. Then, if you estimate a one-month task as four
| months, you will likely not win three months to spend on
| other tasks. You'll probably spend the whole four months on a
| one-month task instead.
|
| Another issue: if you are competing for a project, over-
| estimates will translate in higher than necessary costs, and
| you may end up overpricing a project and missing the
| opportunity.
|
| However, as I said, I don't judge and I also recur to that
| more often than not. On many Organizations, there aren't many
| other ways to deal with the matter. And that's why I say that
| the entire Organization looses: managers will have a good
| night of sleep after putting all the burden over your
| shoulders, but the losses are affecting every single
| stakeholder.
|
| It's about time for them to start behaving a bit more
| responsibly.
| brainbag wrote:
| When I am leading teams, I also ask for a certainty score along
| with the estimate, then track them together with daily updates.
| Like all human processes it is not infallible but it allows
| more reliable planning. I always wish I had a tool that would
| include this in the estimate process. Hansoft got close but
| nobody uses it!
| edu-ap wrote:
| if you use JIRA you can do it with a tool like this one and use
| past performance as input so you don't need to model anything
| https://marketplace.atlassian.com/apps/1216661/actionableagi...
| mfbx9da4 wrote:
| The issue with focusing on realistic estimates is it omits the
| psychology of deadlines, incentives, ownership, competitiveness
| and determination.
|
| Going back to your university days, who hasn't left things to the
| last minute and been amazingly productive in the last couple days
| before the coursework or exam was due?
|
| The issue with aggressive deadlines is burnout, creative
| oppression, flawed risk management etc
|
| As always it's a balance. Grass is always greener but chances are
| it's neither.
| JDDunn9 wrote:
| You don't need a monte carlo simulation if you have a known
| distribution. You can just add the means and variances and solve
| the equation rather than approximating it with a simulation.
| Monte carlo is more useful when drawing from an unknown
| distribution.
| jacques_chester wrote:
| My understanding is that while the normal distribution is
| friendly to simple manipulation, a lot of distributions aren't.
| Not being a statistician I couldn't tell you why or which.
| streamofdigits wrote:
| A Monte Carlo simulation can hide a lot of assumptions about the
| the actual system being modelled and the distribution of random
| variables (both on a univariate basis and as a dependency).
|
| Its flexibility and power of estimating (otherwise maybe
| untractable) metrics comes at the expense of transparency,
| potential simulation noise and difficulty in estimating accurate
| "what if" scenarios. The risk is that one might get out simply
| what one assumes.
|
| Here a list of questions you can ask to minimize the associated
| risks and steer your development:
|
| * Do I have a good, self contained, description of the system
| that I want to simulate? Is it even possible to define it in
| practical terms?
|
| * Do I have historical data that can pin down its stochastic
| behavior? Can I estimate a statistical model reliably?
|
| * Does the uncertainty around model estimation justify retaining
| the full model or could I possibly simplify it and obtain semi-
| analytic results?
|
| * Can I validate my estimates out-of-sample
| BoppreH wrote:
| I love small simulations like this, but I find tiresome writing
| all the scaffolding to summarize the results. So I wrote this
| Python module:
|
| https://github.com/boppreh/carlo pip install
| carlo carlo "d(20)+randint(2, 5)+int(random()*20)"
|
| This will continually generate samples and show them in a self-
| updating histogram.
|
| This is harder than it looks, because there's too many samples to
| store them all, and we don't know the range of values at start.
| But I'm quite happy with the results.
| ImaCake wrote:
| That is pretty neat! I have a dice stats python script I use
| specifically for DnD. It has command line flags and basically
| the same syntax as the discord dice bot. Very useful when you
| are considering strategy, even though my group plays fast and
| loose with the DnD rules.
| Guffton wrote:
| It would be good to build a company corpus using completed .mpp
| files.
| dognotdog wrote:
| A nice exposition! I think Omniplan does this [1], and it
| certainly helped me in the past get a better idea on variability
| of long-term project planning. Of course, it's only as good as
| the assumptions that go into it!
|
| [1] https://www.omnigroup.com/omniplan/features/#Monte-Carlo-
| Sim...
| chromanoid wrote:
| I recommend the book "Software Estimation: Demystifying the Black
| Art" (2006) by Steve McConnell. Nice collection of excerpts:
| https://leventov.medium.com/excerpts-from-software-estimatio...
|
| There is also a short chapter on estimation tools using e.g.
| Monte Carlo simulations. One tip which is relevant here and that
| is also more or less presented in the article and probably
| obvious :) "TIP #65: Don't treat the output of a software
| estimation tool as divine revelation. Sanity-check estimation
| tool outputs just as you would other estimates."
| jacques_chester wrote:
| Some other books I can recommend to read alongside McConnell's
| are _Waltzing With Bears_ by DeMarco and Lister (of
| _Peopleware_ fame) and _How to Measure Anything_ by Douglas W.
| Hubbard.