DRIVING THE HOLLOW STEEL PILES TO BED ROCK.

The Foundation of a Sky Scraper

How Hollow Steel Piles, Compressed and Concrete Are Employed to Make a Foundation

Rapidity of building construction is of primary importance in every city of metropolitan size. When real estate is sold at the rate of several hundred dollars a square foot it is self-evident that time is indeed money. The delay of a few days in completing a structure may deprive the owner of the chance of earning thousands in rental money. Because of the excessive depth of an open caisson, the completion of a foundation may be delayed for months. Hence the building may not be completed until the renting period has passed and the owner must wait an entire year before he can expect any financial return on his investment.

Because rapidity is so essential in city building construction the method of first sinking an open pit to rock in providing a foundation has been displaced to a large extent by a system in which heavy hollow steel piles are employed in clusters to support a building. The hollow piles are driven through quicksand to rock, cleaned out and ultimately filled with concrete.

PILES ARE DRIVEN DOWN
TO SOLID ROCK

In this method of constructing foundations, which is illustrated, hollow steel piles are driven in the well-known manner down to solid rock. The steel pile sections vary in length from 20 feet to 22 feet, and in diameter from 12 inches to 24 inches. If the ground is to be penetrated to a depth greater than 22 feet, the sections of piling are connected by means of a sleeve in such manner that a watertight joint is formed. Under a pressure of 150 pounds to the square inch a jet of compressed air is then employed to blow out the earth and water contained within the shell. A spouting geyser of mud rising sometimes to a height of 150 feet, and occasional large pieces of rock blown up from a depth of 40 feet below the ground, bear testimony to the terrific force of the air blast.

THE PILES ARE ABOUT TWENTY-TWO FEET LONG. IF GREAT DEPTHS ARE TO BE REACHED SECTIONS OF PILING ARE JOINED TOGETHER BY MEANS OF A SLEEVE.

When the shell has been completely cleaned out by means of the blast of compressed air, the exposed rock can be examined by lowering an electric light. Steel sounding rods are employed to test the hardness of the rock and to detect the difference between soft and hard bed rock. After the piles in each pier have been cleaned out, they must be cut off at absolutely the same height—sometimes a very difficult task when there is little room. The oxy-acetylene torch is used for the purpose, the intensely hot flame cutting off the steel almost like butter at the exact elevation desired.

CUTTING STEEL PILES WITH A HOT FLAME

PILE BEING CUT TO PROPER LEVEL BY MEANS OF OXY-ACETYLENE TORCH.

After the piles in each pier have been cleaned out they must be cut off at exactly the same height—sometimes a very difficult task when there is little room. The oxy-acetylene torch is used for the purpose, the intensely hot flame cutting off the steel almost like butter.

A CLUSTER OF PILES, CLEANED OUT, FILLED WITH CONCRETE AND CUT OFF FLUSH BY MEANS OF THE OXY-ACETYLENE FLAME.

PILES ARE NEXT FILLED
WITH CONCRETE

The hollow shell is next filled with concrete reinforced by means of long two-inch steel rods, sometimes fifty feet in length. On clusters of these concrete-filled piles, the weight of the building is supported.

That this method of constructing foundations is indeed rapid, the story of the work at 145-147 West Twenty-eighth Street, New York City, proves. Rock was located 38 feet below the curb. The material above it was clay and water-bearing sand. Structural steel was due in three weeks, but the completion of the cellar was still ten days off. The steel pile foundation method offered the only solution of the problem. Specifications were drawn which called for eighty-five 12-inch steel piles, driven to rock, blown clean by compressed air, and filled with concrete, reinforced with 2-inch rods. Despite various obstructions on the ground (shoring of neighboring buildings and the like) the driving was started on June 30th. The excavator was still taking out his runway while the rear half of the lot was completely driven. After he had left the ground a compressor was set up, and the first pipe was blown on July 7th. Three days later all driving and cleaning had been completed. During the following two days all the piles were filled and capped. In a word, the entire foundation had been completed three days before the expected arrival of the steel.

CONCRETE PILES WHICH HAVE BEEN SUNK TO ROCK BOTTOM AND IN WHICH TWO-INCH STEEL RODS HAVE BEEN INSERTED TO ACT AS REINFORCEMENT FOR THE CONCRETE WHICH WILL EVENTUALLY BE POURED IN.

Such rapid work is not unusual with the steel foundation method. On another contract, work was completed not in the three months stipulated, but in exactly one month and a half, during which brief time all the excavation had been done, including sheeting, shoring, pile-driving, the mounting of concrete girders to carry the wall and capping of the piles ready to receive the grillage.

THE STEEL PILE IS EASILY FORCED EVEN THROUGH THE SOFT UPPER LAYERS OF BED ROCK. SOMETIMES VERY LARGE PIECES ARE BLOWN UP INTO THE AIR BY THE BLAST OF COMPRESSED AIR.

Sometimes difficulties are encountered which would prove all but insurmountable and certainly hopelessly expensive with other methods. Thus in carrying out the one contract, water was found 12 feet from the curb. Two running streams had intersected at that point. The piles were simply sunk through the stream to rock bottom without any difficulty.

The excessive cost of open-pit work has sometimes made it impossible to build twelve or fourteen-story buildings in many sections of the city of New York. The steel pile has, however, made steel building construction profitable.

The carrying capacity of a steel pile is enormous. On a single 12-inch steel pile one hundred tons can be safely maintained. Piers containing sixteen piles have been used, and loadings up to 1300 tons are not unusual.

Naturally the question arises: Do the steel piles deteriorate in time? The question has been answered over and over again by the piles themselves. After a service of fifteen years the steel foundation piles were removed from the site of a building which now stands at the northwest corner of Wall and Nassau streets, in New York City. They showed practically no deterioration. The oxidation on the outside was almost negligible.

BLOWING OUT MUD AND ROCK WITH COMPRESSED AIR

CLEANING OUT A HOLLOW STEEL PILE BY MEANS OF COMPRESSED AIR A GEYSER OF MUD ALWAYS APPEARS.