Track project work and cost
The
Resource Sheet contains data (total, actual, remaining, standard, overtime)
regarding the work and cost for resources and their assignments. The data can be seen as totals in the left pane or time
distributed in the right pane.
As the project evolves,
actual data represents the resources (work, cost) already consumed for the completed part of the project.
Remaining data refers to the resources needed for the remaining part of the project.
To see work distribution in time press the
Work button in the View Toolbar.
In the right pane will be available the following information:
- Assigned - planned work resulted from resource-task assignments
- Available - unassigned work that can be done by resources according to their calendar
- Capacity - total work (assigned + available) that can be done by resources according to their calendar
- Actual - performed work according to the completed part of the project
- Remaining - work to be performed to complete the uncompleted part of the project
- Standard - planned work paid at standard rate (planned in the working hours of the resource)
- Overtime - planned work paid at overtime rate (planned beyond the regular working hours of the resource)
- Overallocated - planned work impossible to be done according to the resource calendar and the Max Units value
To see costs distribution in time press the
Cost button in the View Toolbar.
In the right pane will be available the following information:
- Total - total costs for corresponding element in the table, as they are planned
- Actual - costs already incurred for the completed part of the project
- Remaining - costs for the uncompleted part of the project
- Standard - costs with standard work
- Overtime - costs with overtime work