Track project work and cost


The Resource Sheet contains data (total, actual, remaining, standard, overtime) regarding the work and cost for resources and their assignments. The data can be seen as totals in the left pane or time distributed in the right pane.
As the project evolves, actual data represents the resources (work, cost) already consumed for the completed part of the project. Remaining data refers to the resources needed for the remaining part of the project.

To see work distribution in time press the Work button in the View Toolbar. In the right pane will be available the following information:
To see costs distribution in time press the Cost button in the View Toolbar. In the right pane will be available the following information: